Hizmetler

MESS Data Center / Data Center Installation Project

Technological Construction Works

  • Earthquake Stabilization Applications (Cabin, Panel, Air Conditioning Data Center Components)
  • Epoxy Application
  • No Fire Paint Application (Fire Resistant Paint)
  • Ramp Manufacturing
  • Sealing Application
  • Fire Resistant Drywall Application
  • Fire Resistant Door Installation

Electrical work

  • Tier 3 Energy Infrastructure
  • Low Voltage Form 2D Enclosures
  • Led Lighting System
  • Modular UPS and Battery System
  • Grounding and Surge Arrester Solutions

Air Conditioning Systems

  • Precision Air Conditioning System
  • Fire Detection and Extinguishing Systems

  • Novec1230 Extinguishing System
  • Fire detection system
  • Smart PDU, Cabinet and Cold Corridor System

  • Rack Kabinet
  • Intelligent PDU System
  • Structured cabling

  • Cat 6A Copper Cabling System
  • Fiber OM3 and Single Mode Cabling System
  • Steel Wire Basket Application
  • Automation Solutions

  • UPS Monitoring
  • Climate Monitoring and Control
  • Smart PDU Monitoring
  • Energy Monitoring
  • Temperature Detection System
  • Moisture Detection System
  • Liquid Detection System
  • Security systems

  • CCTV Systems
  • Controlled Access Systems (Card Pass, Fingerprint Reading)
  • ---